Fact Finding Report of the Joint Action Committee team on the

status of Nirmala Jyothi and Valmiki Ambedkar Avas Yojana (Vambay) Schemes



The Joint Action Committee decided to constitute a team consisting of Shri Venkataswamy from Samata Sainik Dal (SSD), Shri Keshavmurthy from Madiga Misalarthi Horata Samiti (MRHS), Shri Rajendra from Jan Sahyog, Shri Arul Selva editor of Slum Jagathu and, Shri Clifton D’ Rozario, an Engineeer from Alternative Law Forum (ALF) for a Fact Finding mission into the suspected irregularities in the implementation of Nirmala Jyothi and Valmiki Ambedkar Avas Yojana (Vambay) schemes in several slums across Karnataka.


It was decided that this mission would be conducted in slums across all the districts of Karnataka and that the first phase would look into the status of works in the Class 1 cities of Bellary, Dharwad, Davangere and Chitradurga. To this extent it was decided that the team would visit selected slums in the cities of Hospet, Bellary, Hubli, Davangere and Chitradurga.


Accordingly the team decided on the date of its visit to be 19th – 23rd December 2004. The schedule of the team was as follows:


No.

Name of Slum

City

Date of visit





1.

Sriram Nagar

(behind Rama Theatre)

Hospet

20th December

2.

Khaja Nagar

- do -

- do -

3.

Varkere

- do -

- do -

4.

Siddalingappa Chowki

- do -

- do -





5.

Ambedkar Nagar

Bellary

- do -





6.

New Anand Nagar

Hubli

21st December

7.

Maruthi Nagar Heggere

- do -

- do -

8.

Kanya Nagar

- do -

- do -

9.

Kulkarni Akala

- do -

- do -

10.

Sudagad Chawl

- do -

- do -





11.

Sriram Nagar

Davangere

22nd December

12.

Siddarameshwara Nagara

- do -

- do -





13.

New Santhe Maidan

Chitradurga

22nd December

14.

Kaamana Bhavi

- do -

- do -


The team on visiting these slums also held press conferences at Hubli and Chitradurga to make public its findings. Press reportage of the same are annexed to this report.




Methodology:


The Team before its visit had already contacted various slum groups from the selected cities and informed then about the intended fact finding mission, its scope and intentions. It was requested for these groups to identify those slums in which the Nirmala Jyothi and Vambay schemes had been carried out over the past year for the Team to visit. To this extent the slum groups identified various slums and when the Team arrived in these cities, they were escorted to these slums by the slum groups.


On reaching the slum the Team walked through the slum and had lengthy dialogues with the residents there on their views regarding the various aspects revolving around the implementation of the Nirmala Jyothi and Vambay schemes in specific, and the problems faced by them in general. It must be stated here that the response that the Team received was overwhelming at points with the slum residents coming out in numbers to relate their experiences, problems and suggestions.

Findings:


The main findings of the team can be summarized under the following heads:


Lack of transparency:


In this day and age when there is a universal acceptance of people’s right to information and there is considerable movement towards transparency especially with regard to the implementation of public works it is sorry to yet again encounter processes in which people have been kept in the dark entirely. Not a single resident of the slums met by the Team possessed any information whatsoever about the various works that had been sanctioned for their slum under the Nirmala Jyothi Scheme. Besides the serious problem of lack of transparency it has also spun off associated complexities. For instance when certain works have not been completed in certain slums, on being questioned by the residents the Contractors have replied that the funds sanctioned have been exhausted and hence the work cannot be completed. This is clearly demonstrated in New Anand Nagar in Hubli where the roads, drains and UGD are incomplete due to these reasons.


Another problem that we have found is that of the lack of access to the concerned officials and the Contractors which has only compounded the problem of lack of transparency. In Sriramnagar (behind Rama Theatre) in Hospet, the residents complained that the Engineers and the Contractors are from Bellary and rarely visited the slum. Further, in the event of them coming to the slum the residents were never informed.


Another problem encountered here is that of sub-contracting. In Khaja Nagar in Hospet the residents told us that the Contractor had sub-contracted all the work due to which they were at loss about who to question about the implementation of the various works.


The Team also found that there is lack of transparency even in the Vambay scheme. The residents whose houses are being constructed under this scheme are unaware of the sanctioned plans, item-wise estimates and the details of repayment. Thus while in certain slums the houses built were two-room units in others it was only a one-room unit. Further in some slums outside plastering was done while in others no plastering or flooring was done. Also the lack of access to the design plans has resulted in the Contractors claiming that the foundation depth was sanctioned to be only 1 ½’ and that the foundation sanctioned was only a single or double course.


The lack of transparency has also resulted in the residents of some slums being misled to believe that the works are being carried out by the area MLAs or Councillors.


The conclusion that is obvious is that the people the Scheme is directed towards are being kept in the dark regarding its details in terms of amounts sanctioned and works to be done and this lack of transparency has among other repercussions enabled siphoning off of allocated funds by the officials and the Contractors.


Lack of participation:


The total lack of participation of the slum residents is another important finding of the team. That is to say that neither the Karnataka Slum Clearance Board officials nor the Contractors have sought to involve the slum residents in the implementation of the project in any manner whatsoever.


In fact where the residents have sought to insert themselves in the process by questioning the Contractors or the workers about the quality of work, etc. they have been threatened with stoppage of work. In Khaja Nagar in Hospet it was found that when the residents did raise objections about the inferior and inadequate quality of drain, road and UGD work, the workers immediately discontinued the work for a few days.


No uniformity of work:


As mentioned in the first point there is absolutely no uniformity of work carried out under both the schemes. Therefore in some slums Vambay houses consist of two units while in others it is a single unit house. Another example would be the construction of surface drains where in some slums the quality is good while in others it is downright pathetic. The same goes for roads, water supply and UGD.


Quality of Vambay houses:


The quality of the Vambay houses, as found by the Team, ranges from extremely poor to mediocre at the best with most of the houses falling in the poor category.



Sand for bed concrete! Kaamana Bhavi in Chitradurga

(Ambedkar Nagar in Bellary)


One of the most glaring problems that the Team found was the inferior quality of the Vambay houses. Sriramnagar in Davangere exemplifies this where ever single Vambay house has structural diagonal cracks due to inadequate foundations. The Team learnt that the depth of foundations was only between 1 – 1 ½’ with usage of inadequate cement. The Team was appalled at the fact that these cracks have already started to develop less than a year after they have been constructed.




The general quality of the Vambay houses have been found to be poor with, in most slums, no wall plastering, roof plastering or flooring being done.


Every single family whose house was built under this scheme has contributed substantially in terms of labour, materials and money over and above the sanctioned amounts. In Ambedkar Nagar in Bellary the Team personally witness the ongoing foundation work for several houses where in few the depth was 4’ while in one it was 2’. It was learnt that the Contractor had said that the sanction was only for 2’ foundations and any family desiring deeper foundations had to do the excavations, provide materials and money for such. So some of the families having the capacity to do so contributed and have 4’ foundations while others have only 2’ foundations.


Quality of works carried out under Nirmala Jyothi:


Generally speaking the quality of works under Nirmala Jyothi is poor. The Team learnt and saw for itself that the materials that have been of inferior quality and inadequate.


Roads

The roads that have been laid are of cement concrete and the maximum depth, the Team found, was about 4”. In Sriramnagar (behind Rama Theatre) in Hospet it was found that the depth varies between 2” to 3” while in New Anand Nagar the depth was found to be ½” – 1” only. The insufficient depth of the roads has resulted in it disintegrating less than a year since it was laid. A glimpse at the photos shown below demonstrates this point. While the photos on the first row are of roads in the slums the next row is that of a narrow by-lane in the city of Davangere. Note the thickness of the second cement concrete road and the disintegration in the first one. Such is the shoddiness of work being carried out in terms of road laying in the slums under the Nirmala Jyothi scheme.



CC Roads laid in Sriramnagar (behind Rama Theatre) Hospet




CC Road being laid on a by-lane in the centre of Davangere City


The Team also found that the roads have not been laid with a proper gradient resulting in stagnation of water on the roads. This was reported to the Team by the residents of all the slums where CC Roads had been laid.


It was further found that the road levels are such that it is higher than the threshold and floor level of the houses on either side.


What was also seen was that the laying of CC roads was not completed in the entire slum and several roads were left un-concreted. In some slums like Maruthi Nagar Heggere in Hubli and Sriramnagar in Davangere the roads were not yet laid when the team had visited them.


Under Ground Drainage (UGD)

With regard to the laying of UGD the Team found that it was being done in the most unscientific manner. In Sidalingappa Chowki in Hospet UGD and water pipes laid besides each other. We saw that the water pipes are already cracking and water leaking. The UGD also is inferior quality and the joints are not properly insulated. This immediately gives possibility of the sewage water entering the water pipes and causing contamination that will indeed be very dangerous from the health point of view.



UGD and water line being laid adjacent to each other in Siddalingappa Chowki


The Team also was also told that the UGD line was not being laid in gradient and that there was no use of levels to check the gradient during construction. Further the


In all slums except Ambedkar Nagar in Bellary it was found that though the UGD line was in place, the UGD was dysfunctional. In few slums even the individual connections were not yet taken


In some slums like Sriramnagar in Davangere, UGD was yet to be provided.


Regarding the construction of manholes, the Team saw that the manholes were rather shallow in most slums especially Khaja Nagar. Also the manholes were not provided with covers in few slums and the residents had placed stones and wooden planks over them to prevent people from falling into the open manholes.



Manholes without covers in Sriramnagar


Another important finding of the team is that in few areas the UGD had been laid in the slum but was yet to be connected to any main UGD line. This is a rather pathetic way of laying UGD and the Team was highly disappointed to see such shoddy and un-engineering-like work being carried out in the slums. This was most evident in Khaja Nagar in Hospet and New Anand Nagar in Hubli.


The poor quality of the stone ware pipes that were used was seen in Siddalingappa Chowki and Sriramnagar (behind Rama Theatre) in Hospet. While in Sriramnagar, the Team was told that the pipes gets damaged easily and on an average at least 1 pipe needs replacement every month, in Siddalingappa Chowki the Team saw the pipes being laid and saw for itself the inferior quality 4” SW pipes being used. The 9” SW pipes were of better quality here.


Water

Drinking water was found to be one on the main problems faced by the slum residents and the works done by the Nirmala Jyothi scheme has not in anyway rectified this problem.


It was found that though the water lines had been laid in few areas such as Siddalingappa Chowki there was no water supply since the water is to be supplied from a water tank that is yet to be constructed!


It was also found that Low grade 2” PVC pipes have been used. The Team also learnt that these low grade pipes of 20’ length cost Rs 160/- per length. In Sriramnagar (behind Rama Theatre) in Hospet, where the road had been dug up, the Team saw that the water pipes that have been laid are of such extremely poor quality.



Low grade water pipe in Sriramnagar (Opposite Nazir Industries)


The Team also heard people state that they were sure that the drinking water will never be delivered since they were not connected to any main water supply line and also because of the quality of water pipes used to make the connections. Not only is the quality poor but the fact that it was laid just below the surface (as seen from the above photograph) makes it susceptible to constant breakage. It was also found that the water pipes have not been laid in level. Further, even though water pipes have been laid no connections have been made either to individual houses or to any main line. In few slums even the laying of water pipes has not taken place.


The Team also learnt that in New Santhe Maidan in Chitradurga a Borewell that was sanctioned for this slum was put in Idgah Mohalla more than 1 km away


In all individual water connections were not seen in any slum visited by the Team despite the Nirmala Jyothi project.


With regard to community taps the Team found these to be inadequate for the entire slum and further the frequency of water supply was low. For example in a slum like Khaja Nagar in Hospet where there are 160 families, there are 4 public taps where water is supplied once in 4 days. In New Anand Nagar in Hubli where there are 346 families, Mini water supply has been installed by the Corporation with water being supplied once in a week. This is the only source of drinking water failing which the residents have to access drinking water more than 1 km away.


The public taps have been found to be located near the drains, which is rather unhygienic. In Khaja Nagar in Hospet the public water tap in the slum is near the drain and has no tap only open pipe. So when the drain overflows the dirty water enters the pipe and causes contamination



Public Tap in Khaja Nagar Public Tap in Varkere




Leaking low Grade PVC water pipes running through the drain

in Maruthinagar Heggere


Drains

The quality of construction of drains has been found to be generally poor. The Team saw that the drains were not plastered in most slums while in few even the flooring was not proper. It was also found that the shoulders for the drains were not provided in several slums.


The Team has found that the depth of the drains has not been calculated in accordance with the number of families that would use it and have been laid rather arbitrarily. There is not much of a difference in depths for surface and storm drains.


One common feature of all the drains seen is the stagnation of drainage water all along the length of the drain due to non-observance of levels while laying them. In Khaja Nagar in Hospet, Abdul Sammad said that the stagnation in the drains in the slum causes dirty smell and proliferation of mosquitoes. This makes living here very difficult. Also causes illness and increased hospital expenses. Further visitors to their houses cannot sit in their houses and this is very embarrassing.

The team found that the drains were not being used and were filled with mud and rubble. The residents informed the team that the cleaning of the drain does not take place at all. The Team also saw that the drains were crumbling in various places.



Drains filled with garbage in Ambedkar Nagar in Bellary



Drains that are falling apart in Siddarameshwara nagar in Hubli


As in other items even with regard to drains the Team found that they had not been laid entirely in most slums.



Small drains laid only on one side of the road in New Anand Nagar


In Siddalingappa Chowki, near Yusuf Khan’s house, no drain has been provided and the Contractor has said that it had not been sanctioned. So the family has dug a hole where the sewage water fills up and cleans it manually everyday. This is an unhygienic practice but the family has no choice but to resort to such a practice.


One of the most alarming findings was in New Santhe Miadan in Chitradurga where drains have been laid on only one side of one by-lane of approximately 125’-150’length and apparently Rs 10.60 lakhs have been sanctioned for this.The drains have been constructed of solid cement blocks and covered with granite slabs under the NJ scheme.


In Sriramnagar in Danagere no drains have been provided.


It was also found that in some slums the drains do not lead to any main drainage line and end abruptly at the end of the slum. This the Team found in Maruthi Heggere and New Anand Nagar in Hubli. In Maruthi Heggere no reason has been attributed to this while in New Anand Nagar the reason given for this is that the owner of the field has raised a dispute and refused to allow the drain and UGD line to pass through the field. However, there is an alternative route that could be used that the Contractor has refused to consider the same.



This is also seen in Khaja Nagar and Varkere slums in Hospet. The drains from Khaja Nagar lead out of the slum towards Varkere slum. The drains leading out of Varkere are blocked at the end because a private factory there has raised a dispute regarding the drains. Hence there is no outflow and obvious clogging. The Team was told that there is an ongoing litigation with factory on this matter.


Toilets:

Though not on the agenda of the Team when it was fact finding mission was originally planned, the issues around that of toilets has emerged as an important issue. In almost every slum the Team found that the community toilets were either not provided, or were in unusable condition or constructed but yet to be opened for use by the slum residents.


The worst experience heard was that of the women in Sriramnagar (behind Rama Theatre) in Hospet. The community toilet there is in a pathetic condition. It is overflowing all around and every seat is also overflowing. It is insulting and damaging to the people’s dignity to use these. The women complained vociferously and talked about the humiliation in using these dirty toilets and the other humiliation in using the open space adjacent to the community toilet. When the Team visited the toilet there was a terrible stench all around the toilet. There is a NFE centre for children and anganwadi located adjacent to the community toilet where food is cooked and served for children here. The residents told us that the common flies that rest and feed on the feceas also sit on the children’s food. This is highly dangerous for the children and can easily result in an epidemic. Residents around the community toilet belong to the Madiga and Paramar community and these are the worst affected having to live in the midst of such stench and squalor. Muslim women and others decried the situation and lamented their bad fate and the unconcerned attitude of the officials.


Overflowing toilets at Sriramnagar


The same kind of situation was found at the community toilet at Verkere.



The Team also found that in Kulkarni Akala and New Sudagad Chawl in Hubli and Kamaana Bhavi in Chitradurga toilets had been constructed on a budget of Rs 4 lakhs each but lying unused for various reasons. The same is the case in Siddarameshwara nagara and New Santhe Maidan where toilets have been constructed and yet to be opened for use by the slum residents there.



It is indeed appalling that in some slums something as basic as a toilet is yet to be provided to slum residents while in others it has been constructed and not maintained while in others it is constructed but yet to be opened for public use.


Corruption and gross siphoning off of sanctioned funds:

From the visit the Team has found that there is a serious incidence of allocated funds being siphoned off by the Contractors probably in collusion with the KSCB officials. It is the Team’s view that off the sanctioned work only 25% has been carried out. The remaining has been siphoned off by carrying out lesser works than sanctioned and using lesser materials for construction.

PART II


Details of visit:


HOSPET



  1. Sriram Nagar recorded on official records as ‘Behind Rama Theatre’


According to official records –

No. of families – 306

Population – 1698

Legal status – 3(f) on 16-02-1990

Abstract of project costs for this slum are:


Roads

Drains

Water Supply (Pipe lines)

UGD

10% Contingencies

Total Cost


Surface Drains

Culverts












23,60,937

21,67,690

2,75,313

2,11,025

0

5,01,497

55,16,462


Nirmala Jyothi Scheme – 1st Year Implementation (2002 – 03) budgets are:


CC Roads


(lakhs)

Surface drains (lakhs)

Storm water drains

(lakhs)

Culverts


(lakhs)

UGD


(lakhs)

Water works (lakhs)

Total


(lakhs)








24.95

5.4

8.9

1.12

14.75

0.62

55.74


The slum is located behind Rama Theatre and the team found that the Muslim and Dalit communities comprise almost the entire population residing in this slum. The observations of the team are as follows:


General observations:


Roads:


UGD:


Water:


Drains:


Vambay:


Toilets:


  1. Khaja Nagar


According to official records –

No. of families – 150

Population – 758

Legal status – 3(f) on 28-11-1988

Abstract of project costs for this slum are:


Roads

Drains

Water Supply (Pipe lines)

UGD

10% Contingencies

Total Cost


Surface Drains

Culverts












6,24,445

3,57,720

1,65,188

65,285

6,72,982

1,88,562

20,74,182


Nirmala Jyothi Scheme – 1st Year Implementation (2002 – 03) budgets are:


CC Roads


(lakhs)

Surface drains (lakhs)

Storm water drains

(lakhs)

Culverts


(lakhs)

UGD


(lakhs)

Water works (lakhs)

Total


(lakhs)








9.20

14.50

1.98

0.89

3.70

0.78

31.05


General Comments:


Roads:


UGD:


Water:


Drains:


Vambay:


Toilets:



  1. Varkere


According to official records –

No. of families – 285

Population – 3030

Legal status – 3(f) on 18-11-1983

Abstract of project costs for this slum are:


Roads

Drains

Water Supply (Pipe lines)

UGD

10% Contingencies

Total Cost


Surface Drains

Culverts












13,40,233

9,21,996

2,20,251

1,16,295

9,88,452

3,58,723

39,45,950


Nirmala Jyothi Scheme – 1st Year Implementation (2002 – 03) budgets are:


CC Roads


(lakhs)

Surface drains (lakhs)

Storm water drains

(lakhs)

Culverts


(lakhs)

UGD


(lakhs)

Water works (lakhs)

Total


(lakhs)








7.50

27.20

2.97

0.24

10.55

0.80

49.26


General Comments:


Roads:


UGD:


Water:


Drains:


Vambay:


Toilets:


  1. Siddalingappa Chowki


According to official records –

No. of families – 199

Population – 1603

Legal status – 3(f) on 30-05-1983

Abstract of project costs for this slum are:


Roads

Drains

Water Supply (Pipe lines)

UGD

10% Contingencies

Total Cost


Surface Drains

Culverts












7,64,218

11,07,098

1,83,542

81,906

1,90,595

2,32,736

25,60,095


Nirmala Jyothi Scheme – 1st Year Implementation (2002 – 03) budgets are:


CC Roads


(lakhs)

Surface drains (lakhs)

Storm water drains

(lakhs)

Culverts


(lakhs)

UGD


(lakhs)

Water works (lakhs)

Total


(lakhs)








2.20

21.50

0.00

1.84

5.50

0.19

31.23


General Comments:


Roads:


UGD:


Water:


Drains:


Vambay:


Toilets:


BELLARY


  1. Ambedkar Nagar (Kannada Nagara)


According to official records –

No. of families –

Population –

Legal status –

Abstract of project costs for this slum from the Detailed Project Report for the up-gradation of Slums of 21 Class-1 cities are:

(CHECK FIGURES)

Roads

Surface Drains


Water Supply

UGD

10% Contingencies

Total Cost







5,15,668

1,95,814

1,88,487

8,81,359

1,23,133

13,54,460


General Comments:


Roads:


UGD:


Water:


Drains:


Vambay:


Toilets:




HUBLI


  1. New Anand Nagar


According to official records –

No. of families – 346

Population – 1700

Legal status – 3(F) on 02-07-1999

Outline costs for this slum are:


Roads


(lakhs)

Surface Drains


(lakhs)

Water Supply (lakhs)

UGD


(lakhs)

External Electricity (lakhs)

10% Contingencies (lakhs)

Total Cost (lakhs)








8.87

1.46

3.54

10.84

5.00

2.97

32.68


General Comments:


Roads:


UGD:


Water:


Drains:


Vambay:


Toilets:


Electricity:


  1. Maruthi Nagar Heggere


According to official records –

No. of families – 1152

Population – 4608

Legal status – 3(F) on 23-07-1994

Outline costs for this slum are:


Roads


(lakhs)

Surface Drains


(lakhs)

Water Supply (lakhs)

UGD


(lakhs)

External Electricity (lakhs)

10% Contingencies (lakhs)

Total Cost (lakhs)








1.12